Proposed 100MW Solar Project With Hydrogen Storage
In 2018, Main Engineering Services Limited was contracted by S&C Energy International Limited to carry out Grid Impact Study for a Proposed 100MW Solar Project with Hydrogen Storage to be located at Adaklu in Ghana.
The Project was to develop and integrate a 100MW Solar plant with Green Hydrogen Storage into the National Grid of Ghana. The Project developers are AG Acardia Invest Ltd, Isef Business Consult and S&C Energy International Limited.
The objective of the study was to determine the plant performance on the national grid in terms of frequency and voltage stability, 161kV/34.5kV transformer capacity requirements, 161kV transmission line routing, 161kV substation preliminary design works as well as the substation bus arrangements and breaker configurations.